Key points of construction and installation of coated steel pipe
1). It shall be implemented by "Technical Regulations for Construction Water Supply Plastic Coated Composite Pipeline Engineering" CECS125:2001.
2) The following construction equipment should be used for coated steel pipes:
 (1) Cutting should be done with a metal saw;
 (2) The pressing groove should adopt a special groove rolling machine;
 (3) The pipe bending machine should be cold bending;
 (4) The pipe threading machine should be used for pipe thread processing; 
 (5) Deburring and processing corners of plastic-coated steel pipe ports should be processed with files;
 (6) Small brushes or small toothbrushes should be used to apply high-strength inorganic solvent liquid epoxy resin coatings.

 


Name*
E-mail*
Rate*
Comments*
About the author
jw_23336
Related News